How to use this calculator
- Measure the slab length and width in feet or meters. For an L-shaped pour, split it into rectangles and run the calculator for each.
- Enter the grid spacing. 12–18″ (300–450 mm) each way is typical for slabs and driveways; 12″ for heavy loads.
- Choose the bar size. #4 (½″) or 12 mm suits most residential slabs; #3 or 10 mm for patios on good ground, #5 and up for heavy or structural work.
- Keep the 10% extra for laps and cut-offs, or raise it if your slab is much longer than one stock bar.
- Pick the stock length your supplier sells (20 ft in the US, 6 m or 12 m in metric markets) and enter the price per bar to see the cost.
How the rebar calculation works
Bars run the full length and the full width of the slab, one at every grid line. The number of bars in each direction is the other dimension divided by the spacing, rounded down, plus one for the closing bar. A 20 × 12 ft slab at 16″ spacing gets 10 bars running the 20 ft way (12 ft ÷ 16″ = 9 spaces, so 10 bars) and 16 bars running the 12 ft way: 10 × 20 + 16 × 12 = 392 ft of bar before laps.
The 10% allowance covers lap splices and cut-offs. A standard lap is about 40 bar diameters — 20″ for a #4 bar, 500 mm for 12 mm — and any bar that can't span the slab in one piece needs a lap at every joint. For the 20 × 12 ft slab that's 431 ft of #4 bar, which is 22 stock bars of 20 ft and about 288 lb of steel. At $10 per bar, the grid costs $220.
The two grids cross at every intersection, and each crossing gets a tie: 10 × 16 = 160 ties for this slab. Ties don't add strength — they just hold the grid in position while the concrete is placed — so one quick twist per intersection is enough.
In metric, a 6 × 4 m slab at 400 mm spacing takes 11 bars along the length and 16 across: 130 m of bar, or 143 m with 10% for laps. That's 24 stock bars of 6 m and about 127 kg of 12 mm bar.
Pro tips
- Set the grid on chairs or dobies so the bars end up near the middle of the slab. Rebar lying on the gravel does almost nothing — concrete is strong in compression, and the steel only works where the slab wants to stretch.
- Keep bars 2–3″ (50–75 mm) clear of the forms and the slab surface. Steel that touches the surface rusts, and rust expands and spalls the concrete.
- Cut rebar with an angle grinder, a portable band saw or a rebar cutter — and bend #3 and #4 bars cold around a pipe. Never heat a bar to bend it unless the engineer says so.
- Tie every intersection where bars can slide, and at least every second or third intersection elsewhere. The grid only needs to survive foot traffic and the pour.
- For driveways and vehicle slabs, put the grid in the bottom half of the slab with proper chairs, or better, two layers for heavy trucks. Fiber mesh or welded wire mesh is enough for light patios.
Frequently asked questions
How much rebar do I need for a 20 × 12 ft slab?
At the common 16″ spacing, a 20 × 12 ft slab takes 392 ft of bar: 10 bars running the long way and 16 across. Add 10% for laps and cut-offs and you need 431 ft, which is 22 stock bars of 20 ft, about 288 lb of #4 bar.
What rebar spacing should I use for a concrete slab?
12–18″ (300–450 mm) each way for residential slabs and driveways, with 12″ for heavy vehicles or poor soil. Wider than 18″ and the grid stops controlling cracks effectively in a 4″ slab.
How much does #4 rebar weigh?
0.668 lb per foot (0.994 kg per meter), so a 20 ft stock bar weighs about 13.4 lb (6.1 kg). A 12 mm metric bar weighs 0.888 kg per meter, or 5.3 kg per 6 m bar.
How long should a rebar lap be?
About 40 bar diameters for a simple tension lap: 15″ for #3, 20″ for #4, 25″ for #5, and roughly 400–500 mm for 10–12 mm metric bars. Wire the laps together at both ends and the middle.
Is rebar or wire mesh better for a 4-inch slab?
Both work for light slabs. Welded wire mesh is faster to lay and cheaper, and suits patios and walkways on good ground. Rebar in a 12–18″ grid is stiffer, easier to keep at mid-height on chairs and the better choice for driveways, vehicles and sheds. Wire mesh that ends up on the ground under the concrete adds almost nothing.
What size rebar for a 4-inch driveway slab?
#3 (⅜″) at 12–16″ spacing is the common minimum, and #4 (½″) at 16″ is the usual choice where trucks or an RV will park. In metric, 10 mm at 300–400 mm for light duty and 12 mm at 400 mm for vehicles.
These results are estimates for planning and budgeting. Actual quantities depend on site conditions, products and workmanship. Check structural and code requirements with a licensed professional before you build.